When it may be needed

In BC, employers are required to measure noise where workers may be exposed above the noise exposure limits in Part 7 of the BC Occupational Health and Safety Regulation. The limits are an average of 85 dBA over an 8-hour shift, and a peak sound level of 140 dBC. Where workers are exposed above the limit, a hearing conservation program is required.

A noise assessment may be needed, for example:

The action level and the 3 dB exchange rate

Decibels work on a logarithmic scale. BC uses a 3 dB exchange rate: every 3 dB increase doubles the sound energy, so the time a worker can be exposed without exceeding the limit is halved. For example, 88 dBA for 4 hours gives the same noise dose as 85 dBA for 8 hours.

For the same reason, 82 dBA is half the noise dose of the 85 dBA limit. It is used as an action level, in line with the action level approach in Part 5 of the Regulation (half of the exposure limit). Where noise is at or above the action level, further assessment and controls should be considered. A pre-screening survey, as described in CSA Z107.56, can help decide whether a full assessment is needed.

Types of measurement

Measurements follow recognized methods, such as CSA Z107.56. Results from the meters are available on site, then reviewed and reported after the visit.

What we need from you

How it works

01

Site walkthrough and plan

We visit the site to review the work areas, equipment and tasks, then agree which workers, jobs and areas to measure, and when.

02

Measurements on site

Sound level readings are taken at work areas and equipment, and workers wear dosimeters during their shift.

03

Review of the results

The measurements are reviewed and the daily noise exposures are calculated.

04

Report

You receive the results, compared against the exposure limits, with observations and recommendations.

What you receive

A report with the measured sound levels and worker noise exposures compared against the exposure limits, what we observed about the noise sources and controls, and recommendations, for example on noise controls, hearing protection, signage and your hearing conservation program.

Limitations

Quotes and proposals

Quotes are not given verbally over the phone: where practical, we review the site first, then send a written proposal with the scope and deliverables.

Scheduling, cancellations and site readiness

Site visits are booked around your schedule, and our staff travel to site for them, so please let us know as early as possible if the work is delayed or the visit needs to change. Fees for cancellations, rescheduling, no-shows, and waiting time on site (for example, when the work area, access or the people involved are not ready when we arrive) apply as set out in your proposal.

Turnaround

Turnaround times for results and reports are set out in your proposal. Rush turnaround is available on request; a surcharge applies.