Noise monitoring
What a noise assessment involves, when it may be needed, and how the results are used.
When it may be needed
In BC, employers are required to measure noise where workers may be exposed above the noise exposure limits in Part 7 of the BC Occupational Health and Safety Regulation. The limits are an average of 85 dBA over an 8-hour shift, and a peak sound level of 140 dBC. Where workers are exposed above the limit, a hearing conservation program is required.
A noise assessment may be needed, for example:
- When people have to raise their voice to be heard by someone about an arm's length away.
- When new equipment, processes or work areas are introduced, or existing ones change.
- When setting up or reviewing a hearing conservation program, or choosing hearing protection.
- When shift lengths change, since longer shifts can increase a worker's daily exposure.
- As the outcome of a gap analysis, or in response to a regulatory order.
The action level and the 3 dB exchange rate
Decibels work on a logarithmic scale. BC uses a 3 dB exchange rate: every 3 dB increase doubles the sound energy, so the time a worker can be exposed without exceeding the limit is halved. For example, 88 dBA for 4 hours gives the same noise dose as 85 dBA for 8 hours.
For the same reason, 82 dBA is half the noise dose of the 85 dBA limit. It is used as an action level, in line with the action level approach in Part 5 of the Regulation (half of the exposure limit). Where noise is at or above the action level, further assessment and controls should be considered. A pre-screening survey, as described in CSA Z107.56, can help decide whether a full assessment is needed.
Types of measurement
- Sound level surveys use a calibrated sound level meter to measure noise at work areas and equipment. They help identify the noisy areas and sources, and where hearing protection or signage may be needed.
- Personal noise dosimetry uses a small, calibrated meter worn by a worker during the shift, to measure that worker's noise exposure for comparison with the exposure limit.
- Environmental noise measurements, for example in response to a noise complaint, measure noise levels at a location so they can be compared with municipal noise bylaws, where these exist. A sound level meter measures how loud it is, but cannot confirm which direction the noise is coming from.
Measurements follow recognized methods, such as CSA Z107.56. Results from the meters are available on site, then reviewed and reported after the visit.
What we need from you
- A description of the work areas, equipment and tasks, and which workers, jobs or areas you want assessed.
- Your hours of operation and shift lengths, and availability for a preliminary walkthrough of the site before we prepare the proposal.
- The work schedule, so measurements are taken during normal operations, with the equipment running as it usually does.
- A site contact to accompany us on the day, and workers available to wear dosimeters for their shift and, where needed, to note their tasks on a form we provide.
- Any existing hearing conservation program, previous noise surveys, and site orientation or PPE requirements.
- Anything we should know about site safety: unsafe areas, structural issues, animals, or other hazards.
- Any stop-work order on the site from the municipality or WorkSafeBC. We cannot carry out work on a site under a stop-work order without their permission.
- Confirmation of whether photographs are permitted on site.
How it works
Site walkthrough and plan
We visit the site to review the work areas, equipment and tasks, then agree which workers, jobs and areas to measure, and when.
Measurements on site
Sound level readings are taken at work areas and equipment, and workers wear dosimeters during their shift.
Review of the results
The measurements are reviewed and the daily noise exposures are calculated.
Report
You receive the results, compared against the exposure limits, with observations and recommendations.
What you receive
A report with the measured sound levels and worker noise exposures compared against the exposure limits, what we observed about the noise sources and controls, and recommendations, for example on noise controls, hearing protection, signage and your hearing conservation program.
Limitations
- Results describe the equipment, tasks and conditions on the day of the measurements. Different production levels, equipment or tasks can give different results.
- A limited number of dosimeter measurements may not represent every worker, job or shift; more measurements may be recommended.
- It is difficult to follow several workers around a site all day to record what they were doing and when. Workers may be asked to help by noting their tasks on a form we provide, and the results depend on those notes.
- Environmental noise measurements show the noise level at the measurement location, but cannot confirm its direction or source.
- A noise assessment is not a hearing test. Workers' hearing tests are a separate part of a hearing conservation program.
- Where available, previous reports or results by others may be used for reference. They are relied on only with permission and where the information can be verified.
- Our findings can only be as complete and accurate as the information provided to us.
Quotes and proposals
Quotes are not given verbally over the phone: where practical, we review the site first, then send a written proposal with the scope and deliverables.
Scheduling, cancellations and site readiness
Site visits are booked around your schedule, and our staff travel to site for them, so please let us know as early as possible if the work is delayed or the visit needs to change. Fees for cancellations, rescheduling, no-shows, and waiting time on site (for example, when the work area, access or the people involved are not ready when we arrive) apply as set out in your proposal.
Turnaround
Turnaround times for results and reports are set out in your proposal. Rush turnaround is available on request; a surcharge applies.
Related guides
Ready to talk about your project?
Send the project details and we will follow up to talk through the plan.